10 June
June 10, 2020 2:05 pm8TH JUNE TO DECEMBER
From 8th June until 22nd December 2020, seven pay and display parking bays will be suspended to allow for two-way temporary traffic management and a lorry holding corridor along the façade of West Hall, on Blythe Road.
22ND JUNE FOR TWO WEEKS
It will be necessary to close a section of Blythe Road at the junction with Beaconsfield Terrace Road to vehicular traffic from 22nd June 2020 for approximately two weeks. A local diversion will be in place.
1ST JUNE FOR FIVE WEEKS
A subcontractor, Reach Active, will undertake excavation works on sections of Blythe Road and Beaconsfield Terrace Road. These works are required to install HV infrastructure which will improve energy efficiency for the delivery