A 100t mobile crane base unit will arrive from 06:30 via G-Gate. It will be parked on Central piling mat before rigging commences from 08:00.

Only hand tools will be used, and all best practice mitigation measures will be implemented.

 Friday 10th December 2021 – G-Gate, Blythe Road/Hammersmith Road

Concrete pouring of the groundfloor slab will commence from 07:00 and allowing for any delays, completion of concrete pours will be at 20:00. Closedown activities will be complete by 21:00.

Please expect up to 4 concrete wagons to arrive per hour. All relevant mitigation measures will be implemented