30 March

March 30, 2022 9:35 am Published by

Works will be undertaken between 7am and 9pm on 30th March. This will involve the use of the electric crawler crane, a piling rig, an excavator and deliveries by a concrete wagon.

7am – 8am – Complete excavation using the piling rig, this will be for around 30 minutes.
8am – 8pm – Installation of the cage and pouring of concrete.
8pm – 9pm – Completion of concreting, and the removal of the temporary casing. This will involve using the piling rig.
Works will follow best practicable means, including switching off engines when not in use, and the use of a silenced Kelly bar. Operatives onsite will also be kept to the required minimum.

Care will be taken to ensure as minimal disturbance to residents as possible.